What have you done this week?

  • Solve difficulties merging branches to a master when a conflict has occurred in the updates of the packages and classes.
  • Test and verify that the current implementation complies and passes testing before merge.
  • Create classes for the hibernate package that are used to pass information to and from the database.
What challenges did you occur?
  • I had to figure out how to resolve class conflicts in the repository after changes have been made in the same class after updating. I ended up learning how to use a merge tool inside Eclipse.
What will you do next week?
  • We will assign additional task regarding the reconstruction of the API's and their end to end communication.
  • Attempt to complete beta version for next week live testing.
  • Stabilize bugs found.