Sunday, February 9, 2014

SE591 Week 5 - Blog post: Vaclav

What have you done in the last week?

  • Found and patched major issue with JSON
    • CORS header logic missing.
    • this was confusing http requests from outside the system
  • Ran testes and edited all submitted code to Server
  • Assisted in posting new code base to hosted server
  • Created more API layouts for use by the team
  • Repaired issue in one of the branches to help migrate the data to master
What were your challenges?
  • Had a delay with BETA, we were unable to get communication to go from webpage to server. Frustrating and took a long time to find the issue.
What do you plan of doing this week? 
  • Test website readiness for User testing
  • Add last APIs that are missing from basic web experience
  • Assist others in code or documentation

No comments: